According to the operation principle of our parking system, the periodical maintenance should be fulfilled as per the following four types:
A.Monthly inspection and maintenance
It should be done every two weeks after project starts to operate within the fifirst three months.
The equipment and safety devices should be clean, lubricated adjusted inspected. Especially, please pay more attention on the working status of main safety devices, careful inspection is necessary and please fifix any problem found out in the earliest time. Do inspection on every lubrication parts, and lubricate it if needed.
B.Quarterly inspection and maintenance
It should be done every three months after fifirst moths end.
All the transmission parts (steel cables, limit switches, motor in power pack, pulleys, guiding rails, etc.), safety devices and electrical control system should be inspected completely, and do necessary adjusting or fifixing work if needed.
C.Yearly inspection and maintenance
A technical inspection of whole equipment (including earth connection and withstand voltage of electrical parts, etc.) should be done every year, and customer need make estimation on working status of equipment and annual maintenance plan, fifix and replace the worn parts.
D.Adjusting test
The adjusting test with loading should be done every two years. The equipment could start to operate only after careful inspection on whole system if there is long time stop or any earthquake, fifire happening.